Skip to main content

Rebuild Committee: October Updates and Construction Report


October 2024 Rebuild Update

Great progress is being made, and the committee has been hard at work coordinating with various contractors and teams to ensure everything runs smoothly.

Pool and Pavilion: 
Plumbing and electrical stub-outs have been completed, and the main concrete slabs have been poured. Blocks for the buildings have been delivered as additional concrete work progresses. The committee is collaborating with the designer on material and finish selections. Work is also ongoing to restore power and water access to the site. The project remains on schedule, with the pool and pavilion expected to be open for use this spring.

Riverhouse and Gym: 
The committee is working closely with multiple teams to finalize a guaranteed maximum price (GMP) for the project. This will be presented to the HOA board and neighborhood at the December board meeting.

Pier access will continue to be via Big Saltmarsh Lane and the bay trail, as the Complex site is an active construction zone. 

-----

Addressing Rumors with Facts

Rumor: "This project will take years."
FACT: The Pool and Pavilion are scheduled for completion in early 2025. The Gym and Riverhouse will begin once approved, with a projected 12-month build time.

Rumor: "The Riverhouse is reducing in size by over 1,000 sq. ft."
FACT: While the unused third floor is being removed, the usable space on the second floor is actually increasing by 1,100 sq. ft., resulting in a net gain of 100 sq. ft. Layout will be significantly improved, and the ground floor is being redesigned to provide better storage and more functional space for neighborhood use.  Additionally, The Gym will see a 325 sq. ft. increase as well as a 1000+ sq. ft screened flex space below for outdoor fitness. 

Rumor: "The HOA is removing amenities, and the building will be a cheap downgrade."
FACT: The committee is focused on reducing high recurring expenses to keep HOA dues reasonable while improving the buildings to better serve the needs of a residential neighborhood. We are committed to making high-quality finish decisions that will reinforce Rivercamps’ standing as the flagship neighborhood in West Bay.

Rumor: "The redesign was done without neighborhood input."
FACT: The committee has held numerous meetings and surveys to gather feedback from residents and has worked with the original architect to create a design that remains true to Rivercamps’ character. Additionally the Committee has maintained an open-door policy for any questions from residents.







Popular posts from this blog

Rebuild Committee: June update and photos

  Rebuild Update – End of May/Early June Thank you for your continued patience—it's been a little while since our last update, and we've made significant progress. Some late-stage electrical changes required by the county caused minor delays, but we’ve now completed several key milestones: Final painting is complete. Most plumbing and electrical punch list items have been addressed. Polycarbonate privacy panels were installed in the bathrooms. Grills and safety timers have been installed. A portion of the new furniture has arrived, and been inventoried and inspected. Access control systems and security cameras were installed. The pool resurfacing is complete and the pool has been filled to begin equipment testing and water treatment. Because the commercial pool equipment has been sitting idle with stagnant water in it for over two years, it must undergo deep cleaning and thorough testing. To meet current commercial pool standards, the water must be properly balanced and circula...

Rebuild Committee: May Photo Update

Rebuild May Update  We’re in the home stretch for completing the pool and pavilion! There have been significant changes since our last update, the most noticeable being the new landscaping, which is really starting to bring the area to life. The pavilion screening has been installed, and access control and security system work is actively underway. Pool pavers are complete, and new pool ladders have been installed. Inside the pavilion, countertops, fixtures, and appliances are all in place and ready to go soon. Pool resurfacing is now in progress, and crews are working through the final touches on electrical, plumbing and various finishing touches. These last steps are coming together quickly, and we’re excited to see the full vision take shape. We appreciate your continued patience and support as we move toward reopening. More updates with an opening date to follow soon!

Community Work Day: Main Gate Beautification

A huge thank you to all the incredible community members who came out to help plant 85 lantana at the main gate and tidy up the landscaping! Your hard work and dedication truly reflect the spirit of River Camps. It’s amazing what we can accomplish when we come together—our entrance is looking more beautiful than ever! - Randy Merritt, Board Member