November 2024 Rebuild Update

Exciting Progress on the Pool Complex!

Things are starting to take shape as the pool complex buildings go vertical and framing gets underway. Over the next few weeks, you'll see even more progress with additional framing and siding being installed. The committee is still aiming for a spring opening to ensure everything is ready for swimming season!

Pool and Pavilion Updates:
Construction is moving full steam ahead, but the committee has identified several areas needing repair and improvement that were outside the original project scope. We presented these findings to the board during the November meeting, and the necessary change order has been approved. We anticipate another presentation soon as we finalize new finishes and furniture selections. 

Riverhouse and Gym Updates:
The committee continues to collaborate with the architect and builder to finalize the Guaranteed Maximum Price (GMP) for presentation to the neighborhood. However, unexpected requirements from the county, coupled with the holiday season, have adjusted the timeline slightly. We now expect to receive the GMP in early January.

----

As the project progresses, we want to keep everyone informed about how we’ve reached this point. Below is an approximate timeline outlining the key milestones leading up to where we are today and some photos of the journey. 

Thanks for the support,

Rebuild Committee



- As a reminder, Pier access will continue to be via Big Saltmarsh Lane and the bay trail, The Complex site is an active construction zone. -







Popular posts from this blog

Rebuild Committee: June update and photos

  Rebuild Update – End of May/Early June Thank you for your continued patience—it's been a little while since our last update, and we've made significant progress. Some late-stage electrical changes required by the county caused minor delays, but we’ve now completed several key milestones: Final painting is complete. Most plumbing and electrical punch list items have been addressed. Polycarbonate privacy panels were installed in the bathrooms. Grills and safety timers have been installed. A portion of the new furniture has arrived, and been inventoried and inspected. Access control systems and security cameras were installed. The pool resurfacing is complete and the pool has been filled to begin equipment testing and water treatment. Because the commercial pool equipment has been sitting idle with stagnant water in it for over two years, it must undergo deep cleaning and thorough testing. To meet current commercial pool standards, the water must be properly balanced and circula...

Rebuild Committee: May Photo Update

Rebuild May Update  We’re in the home stretch for completing the pool and pavilion! There have been significant changes since our last update, the most noticeable being the new landscaping, which is really starting to bring the area to life. The pavilion screening has been installed, and access control and security system work is actively underway. Pool pavers are complete, and new pool ladders have been installed. Inside the pavilion, countertops, fixtures, and appliances are all in place and ready to go soon. Pool resurfacing is now in progress, and crews are working through the final touches on electrical, plumbing and various finishing touches. These last steps are coming together quickly, and we’re excited to see the full vision take shape. We appreciate your continued patience and support as we move toward reopening. More updates with an opening date to follow soon!

Community Work Day: Main Gate Beautification

A huge thank you to all the incredible community members who came out to help plant 85 lantana at the main gate and tidy up the landscaping! Your hard work and dedication truly reflect the spirit of River Camps. It’s amazing what we can accomplish when we come together—our entrance is looking more beautiful than ever! - Randy Merritt, Board Member